Automation Validation & Equipment Buyoff

Holding new automation to its throughput and production requirements, and taking it through buyoff with suppliers.

My role
Controls Engineer
Timeframe
General Motors · Oct 2023 – Present
Team / context
General Motors, Warren, MI
Tech stack
Automation validation · Buyoff checklists · Supplier management · PLC · Open issues tracking · Safety

01

Overview

New automation isn't accepted on a supplier's word. At General Motors I test, validate, and audit automation systems to make sure they meet the throughput and production requirements they were bought for.

I make sure suppliers meet their project deliverables through each project phase, complete the engineering execution checklists that the equipment buyoff process requires, and modify controls logic when process changes are approved. Persistent issues are escalated to senior leadership and tracked on the open issues list until they're closed.

02

The problem & objective

Automation is delivered by suppliers across several project phases. Without a disciplined acceptance process, equipment could be accepted before it meets its throughput and production requirements.

The objective is to prove every system against its requirements, confirm every supplier deliverable, and keep every open issue owned until it's resolved.

03

My role & responsibilities

Controls Engineer. Delivered as part of my role as Controls Engineer at General Motors.

  • Test, validate, and audit automation systems against throughput and production requirements
  • Make sure suppliers meet project deliverables in each project phase
  • Complete the engineering execution checklists required for equipment buyoff
  • Modify controls logic as needed to implement approved process changes
  • Escalate persistent issues to senior leadership and track them on the open issues list
  • Take part in safety talks and team meetings to build safety awareness

04

Approach & process

  1. Test against requirements

    Run and audit each system against its throughput and production requirements.

  2. Hold suppliers to deliverables

    Check supplier deliverables at each project phase, not just at the end.

  3. Document the buyoff

    Complete the engineering execution checklists that the buyoff process requires, so acceptance rests on evidence.

  4. Control changes

    Modify controls logic only to implement approved process changes.

  5. Escalate and track

    Raise persistent issues with senior leadership and track them on the open issues list until they're closed.

05

Key features & deliverables

  • Validated automation

    Systems tested and audited against throughput and production requirements.

  • Completed buyoff checklists

    Engineering execution checklists completed for equipment buyoff.

  • Open issues list

    Persistent issues escalated and tracked with senior leadership.

06

Challenges & how I solved them

ChallengeHow I solved it
Many suppliers, many project phasesChecking deliverables phase by phase, and recording them in buyoff checklists, keeps each supplier accountable.
Some issues don't go away on their ownPersistent issues are escalated to senior leadership and tracked on the open issues list until they're resolved.

07

Results & impact

  • Automation held to throughput and production requirements before acceptance
  • Equipment buyoff backed by completed engineering execution checklists
  • Persistent issues escalated and tracked to closure with leadership

08

Skills demonstrated & lessons learned

Skills demonstrated: Automation validation · Equipment buyoff · Supplier management · PLC programming · Issue escalation · Safety awareness

Acceptance is an engineering task. A completed checklist is better evidence than a demo that went well.